Terminology

Title: 03. NNPB Forming Process

Procedure Brief Description:
(1) Gob Delivery (2) Baffle Down (3) Plunger Up (4) Plunger Down & Invert
(5) Parison Transfer, (6) Parison Reheat (7) Final Blow (8) Take Out

Procedure Detail Description:
(1) BM Close, PL Kick Back, Gob Loading,
(2) BA Down, PL Up,
(3) PL Down, BA Up, BM Open,
(4) Invert (after short Blank Side Reheat), FM Close
(5) Parison Transfer, NR Open, Revert, NR Close,
(6) Parison Reheat (Blow Side) and Elongation,
(7) BH Down, Final Blow On and Vacuum Assist On, if applicable,
......Final Blow Off and Vacuum Assist Off, if applicable,
......BH Up, FM Open,
(8) TT in and out, after picking up product.

Note: Funnel is generally not applied in NNPB Forming Process.

When you are done, Click: Home or previous page